Henry W. Bloch Executive Hall for Entrepreneurship and Innovation

JE Dunn began limited site activities on Thursday March 29, 2012, with the demolition of the Chancellor’s Residence and the creation of construction phase accessible parking for the Henry W. Bloch School of Management at the Cherry Street entrance to the Bloch School Parking Lot 12.

Entrance to the Bloch School Parking Lot 12 will only be available from Oak Street and exit will be via Oak Street or the Law School drive. The eastern row of parking will be utilized for material storage and the JE Dunn trailer in this initial phase.

It is anticipated that the eastern half of the Bloch School Parking Lot 12 will be closed for additional construction activities the week of April 9th. At that time, changes will also be made to reduce the number of meter spaces in the Law School Parking Lot 45.

With the assistance of the Toy and Miniature Museum, additional Faculty and Staff parking will be available in that lot beginning on Monday, March 12, 2012 and lasting through Spring Commencement.

The closure of the balance of the Bloch School Parking Lot 12 will not occur until after the Spring Commencement.

Cherry Street Parking Structure

The Cherry Street Parking Structure (formerly the Oak Street Parking Garage) was closed, as well as the surface parking lot on the south side of the structure, on May 16, 2011 and will open in August 2012.

Click here to view construction webcam.

Volker Campus Street Closures and Pedestrian Improvements

TROOST BRIDGE AT BRUSH CREEK:

The City of Kansas City, Missouri is near completion on the replacement of the Troost Bridge at Brush Creek. The bridge is open to automobile traffic, but there are still final sidewalk, railing, lane markings, signals and pavement replacements which will happen in the Spring of 2012.

The $13.5 million project will add pedestrian passages along that portion of Troost Avenue and improved storm and sewer water management.

Hospital Hill Street and Sidewalk Disruptions Due to Children's Mercy Hospital East Tower Addition Project

Construction activities are ongoing on Hospital Hill related to expansion plans at Children’s Mercy Hospital. The west lane and sidewalk on Holmes between 25th Street and 24th Street will close, beginning the week of July 5, 2010, and will remain closed until the completion of construction on the Children's Mercy Hospital East Tower Addition.